OPTIMIZATION OF PROJECT TIME AND COST IN PANDEMIC ERA BY TIME COST TRADE OFF METHOD OF UNIVERSITAS NEGERI MEDAN CASE STUDY

Authors

  • Gea Geby Aurora Syafridon Universitas Sumatera Utara
  • Syahrizal Universitas Sumatera Utara
  • Rahmi Karolina Universitas Sumatera Utara
  • Muhammad Agung Putra Handana Universitas Sumatera Utara
  • Maria Christin Universitas Sumatera Utara

DOI:

https://doi.org/10.51510/agregat.v2i2.755

Keywords:

Construction, time, cost, trade off

Abstract

The quality of project construction is constrained by the triangle model of project management, refers to the boundaries of scope, cost and time. The construction project at Universitas Negeri Medan is one of the projects that is experiencing delays and does not meet one of the limitations of triple constraints that must be met by each project. This study has aims to identify the acceleration of project duration using the Time Cost Trade Off method with alternative additions of working hours (overtime) 1 hour, 2 hours, and 3 hours as well as the addition of the number of workers by 10%, 15%, 20%, and 25% from the beginning. From the results of the analysis using this method, it was concluded that the addition of the number of workers as much as 10% from the original is more profitable, where the optimum time of acceleration of the project duration is for 171 calendar days and the optimum cost resulting from the acceleration of the project duration is Rp. 14,059,057,900.00.

Downloads

Download data is not yet available.

References

Buluatie, Nurhadinata, 2013. Optimalisasi Biaya dan Waktu dengan Metode Time Cost Trade Off pada Proyek Revitalisasi Gedung BPS Kota Gorontalo, Jurnal Ilmiah Teknik Sipil Vol.1, No.1, Gorontalo: Universitas Negeri Gorontalo.

Chusairi, Moch. 2015. Studi Optimasi Waktu dan Biaya dengan Metode Time Cost Trade Off pada Proyek Pembangunan Gedung Tipe B SMPN Baru Siwalankerto. Jurnal Rekayasa Teknik Sipil Vol. 2, No. 2. Universitas Negeri Surabaya.

Dannyanti, E., 2010. Optimalisasi Pelaksanaan Proyek dengan Metode PERT dan CPM (Studi Kasus:Twin Tower Building Pasca Sarjana Undip). Fakultas Ekonomi Universitas Diponegoro.

Ervianto, Wulfram. 2004. Aplikasi Manajemen Proyek Konstruksi. Yogyakarta: ANDI.

Ervianto, Wulfram. 2005. Manajemen Proyek Konstruksi, Edisi Revisi. Yogyakarta: ANDI.

Frederika, Ariany. 2010. Analisis Percepatan Pelaksanaan dengan Menambah Jam Kerja Optimum pada Proyek Konstruksi. Jurnal Ilmiah Teknik Sipil, 14 (2).

Gulo, Jernih Putri N. 2015. Analisa Percepatan Durasi Proyek dengan Metode Pertukaran Waktu dan Biaya (Time Cost Trade Off Method) (Studi Kasus : Proyek Perumahan Cemara Kuta – Medan). Medan. Universitas Sumatera Utara.

Kerzner, H. 2000. Project Management: A System Approach to Planning, Schedulling, and Controlling. Singapore: Ningrum, F.G. 2016.

Priyo, M., Sudiro, S., 2017. Studi Optimasi Waktu dan Biaya dengan Metode Time Cost Trade Off pada Proyek Konstruksi : Studi Kasus Proyek Jalan Bugel-Galur-Poncosari Cs. Tahap I, Provinsi D.I. Yogyakarta. Semesta Teknika, 20(2), 172-186.

Setiawan, I., Siboro, I., and Faisal, M., 2021. Optimasi Waktu dan Biaya Proyek Menggunakan Metode Time Cost Trade Off (TCTO). Jurnal Transukma, 3(2), 114 – 128.

Soeharto, Iman. 1990. Manajemen Proyek Industri: Persiapan, Pelaksanaan, Pengelolaan. Jakarta: Erlangga.

Downloads

Published

2022-11-30

How to Cite

Syafridon, G. G. A., Syahrizal, Rahmi Karolina, Muhammad Agung Putra Handana, & Maria Christin. (2022). OPTIMIZATION OF PROJECT TIME AND COST IN PANDEMIC ERA BY TIME COST TRADE OFF METHOD OF UNIVERSITAS NEGERI MEDAN CASE STUDY. Jurnal Ilmiah Teknik Sipil Agregat, 2(2), 44–49. https://doi.org/10.51510/agregat.v2i2.755